The Thu Thiem Tunnel is an underground road tunnel designed to cross the Saigon River in Ho Chi Minh City, the largest city in Vietnam.
The tunnel and associated highway are being constructed to link the Thu Thiem Peninsula to National Highway 1A and provide a new integrated transport route for the country.
The project began in 2004 with $189m capital provided by Japanese ODA (official development assistance) and by a consortium of four Japanese contractors: Obayashi Corporation, Taisei Corporation, the Kumagai-Kajima consortium and Toa Corporation.
The estimated cost of constructing the under-river tunnel and the Thu Thiem road is VND9.86trn.
The tunnel will open in November 2011. It links the Ho Chi Minh City's District 1 with Thu Thiem New Urban Area in District 2.
The Thu Thiem Tunnel is part of the East-West highway project, which is under construction to ease congestion in the inner city as well as from the downtown area to the Mekong Delta Region (Dong Bang Song Cuu Long). The East-West highway project is scheduled to be opened in 2011.
The existing downtown area is linked with Thu Thiem New Urban Area by a number of bridges including the Thu Thiem Bridge, Phu My Bridge and Ba Son Bridge. The tunnel is expected to carry around 45,000 automobiles and 15,000 motorcycles a day in three lanes each way. Capital for the project was provided by the Japanese Bank of International Commerce. The tunnel can also withstand an earthquake of six-point Richter scale and is expected to have a lifespan of 100 years.
Thu Thiem Tunnel construction
"New technology is being used to build the Thu Thiem Tunnel crossing."
New technology is being used to build the Thu Thiem Tunnel crossing of the Saigon River with the 1,490m underwater tunnel as one of the project's most ambitious features.
The immersed tunnel will comprise four sections, each 93m long, 33m wide and 9m high, and weighs 27,000t. The sections have been fabricated at a construction site in Nhon Trach District of Dong Nai Province and are made of reinforced concrete 1m to 1.2m thick.
The tunnel comprises six lanes of which four will be provided for automobiles and two lanes for motorbikes. The tunnel will also have two emergency exit lanes on the sides.
While the tunnel sections were being built the contractors excavated the ground, 13 to 14m under the riverbed. The prefabricated parts were ferried along the Saigon River to the construction site. Contractors then sealed each tunnel section at both sides before placing them in the tunnel dug under the river. The sections of tunnel were joined together in a separate operation.
The first segment of the tunnel was positioned in March 2010, while the second and third were placed in April and May 2010, respectively. The fourth section was tucked with the existing segments in June 2010.
Construction of the immersed tunnel system also included two 1km approach roads at each end of the tunnel. Safety and technology in the tunnel will include state-of-the-art lighting, fire prevention and firefighting systems, a traffic jam warning system, pollution measurement equipment and a system to count passing traffic. Obayashi Corporation is the main contractor on the tunnel project.
As of August 2011, the underwater tunnel project was 95% complete. Test runs, traffic testing and rescue drills will be conducted in October 2011. More than 600 workers and engineers are employed in the construction activity.
Feasibility of the tunnel
In June 1997, the chairman of Ho Chi Minh City People's Committee submitted to the then Prime Minister Vo Van Kiet the final report on the feasibility study of a road at Saigon River.
The study was approved with the selected project to build a tunnel under the Saigon River to link District 1 and Thu Thiem Peninsula in District 2 (a bridge was also considered).
Australian consulting company G Maunsell & Partners, in collaboration with MVA Consultancy, CES Enter, Sumitomo Bank and AIC Maunsell and Japan International Cooperation Agency carried out the feasibility study under assignment by the UK's Overseas Development Agency.
Construction of the tunnel was delayed until 2004 due to difficulties in site clearance and relocation and compensation of families.
Route of the Thu Thiem Tunnel
The tunnel begins from Nam Ky Khoi Nghia-Ham Nghi crossroads in District 1, through Ben Chuong Duong Street and Saigon River before reaching Thu Thiem Peninsula.
"District 2 is expected to become a commercial centre to rival Hong Kong."
The study into the tunnel route also focused on Ham Nghi and Ben Chuong Duong streets.
The maximum slope of the tunnel will be 4% to ensure safety for motorcycles and other types of vehicles moving between District 1 and District 2.
District 2 is expected to become a commercial centre to rival Hong Kong and has undergone an intensive programme of slum clearance.
District 2 covers an area of 700ha and consists of several sections – residences, pools, parks and office sections. Almost all of the intended new buildings will be of 10-40 storeys. Once completed, this new urban area will replace District 1 as the city centre.